Polyurea Manhole Lining & Rehabilitation System

Protect concrete manholes against sulphuric acid (H₂S0₄) attack of the concrete or microbiologically induced concrete corrosion (MICC) and leaks. Liquimix Tufflon P90 polyurea & Civilox LV100 primer extend the service by 20+ years.

Superior Concrete Protection with Liquimix Tufflon P90 & Civilox LV100

Municipal sewer networks and wastewater infrastructure are constantly exposed to hydrogen sulfide (H₂S) gas, biogenic sulfuric acid corrosion, groundwater infiltration, and heavy structural loading. Traditional concrete manholes deteriorate over time, leading to environmental contamination and costly asset failures.The Liquimix Polyurea System combining Civilox LV100 deep-penetrating epoxy primer with Tufflon P90 100% pure polyurea provides an elastomeric, corrosion-resistant protective lining designed to extend manhole service life by 20+ years.

Why Choose Liquimix Polyurea for Manhole Rehabilitation?

1. Rapid Cure & Minimal Bypass Time Unlike conventional epoxy or cementitious coatings that require days to cure, Tufflon P90 gels in 5 seconds and can handle traffic or water immersion within minutes to hours. This dramatically reduces sewer bypass pumping costs and minimizes disruption to municipal traffic.

2. Elimination of Pinholes & Moisture Blistering Concrete outgassing and dampness are leading causes of coating failure in underground structures. Civilox LV100 is a 100% solids, low-viscosity epoxy sealer that deeply penetrates wet or dry concrete pores, sealing the substrate and preventing pinholes before Tufflon P90 is applied.

3. Crack-Bridging & Dynamic Flexibility Ground movement, soil settlement, and thermal expansion cause concrete manhole rings to shift and crack. Tufflon P90 maintains over 350% elongation and permanently elastomeric properties, bridging movement cracks up to 1.5 mm without rupturing or debonding.

4. Resists Biogenic Sulphuric Acid & Harsh Wastewater Chemicals, protecting the manholes from microbiologically induced concrete corrosion. Tufflon P90 is resistant to microbial acid attack, alkalis, petrochemicals, and aggressive industrial effluents.

Before Rehabilitation: Unprotected concrete manhole showing early signs of chemical erosion, surface degradation, and exposure to H₂S gas before priming with Civilox LV100 and lining with Tufflon P90.
Before Rehabilitation: Existing concrete manhole infrastructure requiring high-pressure washing, surface profile restoration, and an elastomeric protective coating against H₂S corrosion.
Pre-Lining Inspection: Internal concrete shaft prepared for high-pressure surface profiling, joint sealing, and elastomeric polyurea coating.
Completed internal application of Tufflon P90 pure polyurea, providing a seamless, elastomeric barrier against H₂S corrosion, biogenic acid attack, and infiltration.

Project completed by TriKing. 

System Specification & Application Workflow

Pro Tip for Applicators: Always schedule Civilox LV100 primer application during the late afternoon or evening when the substrate temperature is dropping to prevent outgassing bubbles caused by rising temperatures.

1. Surface Preparation:

  • Clean concrete substrate in accordance with SSPC-SP13 / NACE No. 6 to expose a clean, sound aggregate profile.
  • High-pressure water jetting or abrasive blasting to remove laitance, fats, grease, and degraded concrete.

2. Patching & Profile Restoration:

  • Fill bug holes, voids, and deep spalls using a blend of Civilox LV100 and Renderfill / Patchfill aggregate.
  • Chamfer internal 90-degree corners with a 20 mm flat cove.

3. Priming with Civilox LV100:

  • Apply Civilox LV100 by roller or airless spray (100–200 microns wet) to deeply penetrate, seal, and strengthen the concrete surface.
  • On highly porous concrete, apply a second pass to guarantee zero pinholing in the polyurea layer.

4. Spray Application of Tufflon P90:

  • Apply Tufflon P90 pure polyurea using plural-component, heated high-pressure spray equipment (e.g., Graco E-XP2 or reactor).
  • Build to a seamless nominal thickness of 3000 microns (3.0 mm) DFT in continuous passes.
  • Inspect for pinhole-free continuity with a high-voltage spark tester if required by specification.

Comparison: Liquimix Polyurea vs. Traditional Manhole Solutions

PropertyLiquimix System (Civilox LV100 + Tufflon P90)Standard Epoxy CoatingsCementitious Mortar / Renders
Gel / Set Time5 seconds20 – 60 minutesHours to days
Return-to-ServiceImmediate to 24 Hours3 to 7 Days7 to 28 Days
Elongation & Flexibility>350% (Permanently Elastomeric)Very low (<5%, Rigid)Rigid (0% Flexibility)
Crack-Bridging AbilityBridges up to 1.5 mm cracksPoor (Cracks propagate through)None
Moisture ToleranceHigh (Civilox seals damp concrete)Moderate to LowHigh (Water-based)
Pinhole ResistanceSuperior (Densely sealed by Civilox LV100)Prone to pinholes from outgassingHighly porous
H₂S & Acid Corrosion ResistanceExcellentGoodPoor (Degrades rapidly under acid)
Impact & Abrasion ResistanceHigh Hardness (Shore 90A) / High TearBrittle under thermal expansionProne to chipping & erosion
VOC / Environmental Impact0 g/L VOC (100% Solids)Often contains solventsCement-based

Protect Your Infrastructure Today.

Don’t wait for biogenic sulfide corrosion or structural leaks to compromise your manhole network. Contact Liquimix for a technical consultation on your manhole rehabilitation or new-build project.

Related News

A Smarter Approach to Sunken Concrete Repair Uneven or sunken concrete can create serious safety problems, affect drainage and interrupt daily operations in warehouses, factories, driveways and other areas. Although replacing the entire concrete slab is an option, it can be expensive, time-consuming and disruptive. PURL-SJ40 polyurethane slab-lifting foam provides

Introduction: The High Stakes of Secondary Containment in Australia Across Australia’s industrial landscapes—from chemical processing plants in Queensland to mining operations in Western Australia and wastewater facilities in Victoria—storing and processing hazardous materials carries immense responsibility. Concrete bunds, containment sumps, and processing floors act as the crucial last line of

Browse the complete Liquimix Flooring Catalogue for a full range of high-performance flooring solutions. Find the right system for your project needs.